Under 29 CFR 1910.269, temporary protective grounds are placed at such locations and arranged in such a manner that the employer can demonstrate will prevent each employee from exposure to hazardous differences in electric potential; the appendix on protective grounding explains that an equipotential zone protects the workers within it and not those wholly or partly outside it. The duty is stated in paragraph (n)(3) and the explanation in Appendix C, section III.C.1.
| Step | Item | Detail |
|---|---|---|
| Source | 29 CFR 1910.269 | Regulation, clause (n)(3) |
| Data record | gloss.temporary-protective-grounding.osha1910-269.placement | Verified 2026-10-28 |
| Entry | Temporary protective grounding | No revisions |
- Subject
- Temporary protective grounding (Glossary)
- Kind
- Standard scope
- Source
- 29 CFR 1910.269, current edition, clause (n)(3), 1910.269 - Electric power generation, transmission, and distribution (with Appendices A to G; Appendix B, Working on Exposed Energized Parts), OSHA. Regulation text. Agency copy of 29 CFR 1910.269
- Also stated in
- 29 CFR 1910.269, paragraph (n)(3) (eCFR current as of 2026-10-26).
Read the reference passage
"Temporary protective grounds shall be placed at such locations and arranged in such a manner that the employer can demonstrate will prevent each employee from being exposed to hazardous differences in electric potential."
29 CFR 1910.269, paragraph (n)(3), eCFR current as of 2026-10-26. Agency copy of 29 CFR 1910.269
The current standard governs; this passage is a public-domain description of the practice dated eCFR current as of 2026-10-26.
- 29 CFR 1910.269, Appendix C, section III.C.1 (eCFR current as of 2026-10-26).
Read the reference passage
"An equipotential zone will protect workers within it from hazardous step and touch potentials. (See Figure 3.) Equipotential zones will not, however, protect employees located either wholly or partially outside the protected area. The employer can establish an equipotential zone for workers on the ground, with respect to a grounded object, through the use of a metal mat connected to the grounded object."
29 CFR 1910.269, Appendix C, section III.C.1, eCFR current as of 2026-10-26. Agency copy of 29 CFR 1910.269
The current standard governs; this passage is a public-domain description of the practice dated eCFR current as of 2026-10-26.
- 29 CFR 1910.269, paragraph (n)(3) (eCFR current as of 2026-10-26).
- Beside
- gloss.temporary-protective-grounding.nfpa70e.steps
History
| Date | Change |
|---|---|
| 2026-10-28 | created |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Data record gloss.temporary-protective-grounding.osha1910-269.placement." Arc Flash Reference. 2026-10-28. https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.placement/.
Arc Flash Reference, Data record gloss.temporary-protective-grounding.osha1910-269.placement (Oct. 28, 2026), https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.placement/.
@misc{etr-data-gloss-temporary-protective-grounding-osha1910-269-placement,
title = {Data record gloss.temporary-protective-grounding.osha1910-269.placement},
howpublished = {\url{https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.placement/}},
organization = {Arc Flash Reference},
publisher = {Arc Flash Reference},
year = {2026},
note = {last substantive change 2026-10-28}
}{{cite web |title=Data record gloss.temporary-protective-grounding.osha1910-269.placement |website=Arc Flash Reference |publisher=Arc Flash Reference |url=https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.placement/ |date=2026-10-28 |access-date=}}