Data record gloss.temporary-protective-grounding.osha1910-269.grounds-before-work
Verified 2026-10-28 Confidence: High
Under 29 CFR 1910.269, transmission and distribution lines or equipment are worked as de-energized only after protective grounds have been installed under the grounding provisions of the section, and the lines may be considered de-energized only once the de-energizing steps, the grounding included, have been followed. The duties are stated in paragraph (m)(3)(vii) and the paragraph that follows it, and again in paragraph (n)(2).
| Step | Item | Detail |
|---|---|---|
| Source | 29 CFR 1910.269 | Regulation, clause (m)(3)(vii) |
| Data record | gloss.temporary-protective-grounding.osha1910-269.grounds-before-work | Verified 2026-10-28 |
| Entry | Temporary protective grounding | No revisions |
- Subject
- Temporary protective grounding (Glossary)
- Kind
- Standard scope
- Source
- 29 CFR 1910.269, current edition, clause (m)(3)(vii), 1910.269 - Electric power generation, transmission, and distribution (with Appendices A to G; Appendix B, Working on Exposed Energized Parts), OSHA. Regulation text. Agency copy of 29 CFR 1910.269
- Also stated in
- 29 CFR 1910.269, paragraphs (m)(3)(vii) and (viii) (the ellipsis drops the item numeral) (eCFR current as of 2026-10-26).
Read the reference passage
"The employer shall ensure the installation of protective grounds as required by paragraph (n) of this section. [...] After the applicable requirements of paragraphs (m)(3)(i) through (m)(3)(vii) of this section have been followed, the lines and equipment involved may be considered deenergized."
29 CFR 1910.269, paragraphs (m)(3)(vii) and (viii) (the ellipsis drops the item numeral), eCFR current as of 2026-10-26. Agency copy of 29 CFR 1910.269
The current standard governs; this passage is a public-domain description of the practice dated eCFR current as of 2026-10-26.
- 29 CFR 1910.269, paragraph (n)(2), first sentence (eCFR current as of 2026-10-26).
Read the reference passage
"For any employee to work transmission and distribution lines or equipment as deenergized, the employer shall ensure that the lines or equipment are deenergized under the provisions of paragraph (m) of this section and shall ensure proper grounding of the lines or equipment as specified in paragraphs (n)(3) through (n)(8) of this section."
29 CFR 1910.269, paragraph (n)(2), first sentence, eCFR current as of 2026-10-26. Agency copy of 29 CFR 1910.269
The current standard governs; this passage is a public-domain description of the practice dated eCFR current as of 2026-10-26.
- 29 CFR 1910.269, paragraphs (m)(3)(vii) and (viii) (the ellipsis drops the item numeral) (eCFR current as of 2026-10-26).
- Beside
- gloss.temporary-protective-grounding.nfpa70e.steps; std.nfpa-70e.structure.120-6-8-9-grounding; gloss.temporary-protective-grounding.definition
History
| Date | Change |
|---|---|
| 2026-10-28 | created |
Cite this page
Cite the governing standard for the fact itself; cite this page as the finding aid.
"Data record gloss.temporary-protective-grounding.osha1910-269.grounds-before-work." Arc Flash Reference. 2026-10-28. https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.grounds-before-work/.
Arc Flash Reference, Data record gloss.temporary-protective-grounding.osha1910-269.grounds-before-work (Oct. 28, 2026), https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.grounds-before-work/.
@misc{etr-data-gloss-temporary-protective-grounding-osha1910-269-grounds-before-work,
title = {Data record gloss.temporary-protective-grounding.osha1910-269.grounds-before-work},
howpublished = {\url{https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.grounds-before-work/}},
organization = {Arc Flash Reference},
publisher = {Arc Flash Reference},
year = {2026},
note = {last substantive change 2026-10-28}
}{{cite web |title=Data record gloss.temporary-protective-grounding.osha1910-269.grounds-before-work |website=Arc Flash Reference |publisher=Arc Flash Reference |url=https://www.arcflashreference.com/data/gloss.temporary-protective-grounding.osha1910-269.grounds-before-work/ |date=2026-10-28 |access-date=}}